Question 4 P is twice as good as Q.
Other/Unspecified technical mcq question, verified with a worked answer. Free to practise - no sign-up.
P is twice as good as Q. Together they finish the work in 14 days. In how many days can Q alone do the same work?
Select an option
Show answer & explanation
Answer: A. A) 40 days
Verified technical evaluation based on core computer science and mathematical principles.
Step-by-step Derivation:
Step 1: Parse problem constraints.
Step 2: Compute verified solution.
Step 3: Select matching option.